BIG DIPPER RD CERT OF COMPLETION_., ~~ Certificate of Substantial Completion Project: Owner: Owner's Contract no.: Big Dipper Road Jefferson County N/A Im rovements Contract: Date of Contract: Bi Dipper Road Improvements Jul 16, 2008 Contractor: Engineer's Project No.: Bullock Contracting, Inc. 1-05154 This definitive Certificate of Substantial Completion applies to: O All Work under the Contract Documents: ^ The following specified portions: September 23. 2008 Date of Substantial Completion The Work to which this Certificate has been inspected by authorized representatives of Owner, Contractor and Engineer, and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby declared and is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below. A tentative list of items to be completed or corrected, is attached hereto.. This list may not be all-inclusive, and the failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. The responsibility between OWNER and CONTRACTOR for security, operation, safety, maintenance, heat, utilities, insurance and warranties shall be as provided in the Contract Documents except as amended as follows: ^ Amended Responsibilities: ~ Not Amended: Owner's Amended Responsibilities: Contractor's Amended Responsibilities: One near warranty begins on date of substantial completion. Contractor must complete punch list items within 10 days of the above date of Substantial Completion. The following documents are attached to and made part of this Certificate: See attached punch list This Certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor is it a release of Contractor's obligation to complete the Work in accordance with the Contract Documents. by RECEIVED Acce Contractor ccepted by Owner ocT o s izoo8 GreatWest Date Date /~-~ ~8 Date EJCDC No. C-625 (2002 Edition) Page 1 of 1 Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specification Institute. _... ,. Big Dipper Road Improvements Project PUNCH LIST September 23, 2008 1.) Burm of gravel in cul-de-sac, Northeast side. 2.) Burm along ditch on the South side from cul-de-sac to paved driveway. 3.) Potholes by mailboxes